Case Study | Soho House & Co

Site: 40 Greek Street, Soho, London. W1D 4EB
Project Value: £15-20M
Clients’: 1 Soho House & Co
                2 Interxion

In 2016, Soho House & Co appointed STAP Structural Engineering Services as Temporary Works Designers. STAP designed the Hoarding and the Temporary Underpinning to begin with.

The next phase of STAPs’ work included the Shoring Design for the Basement, Temporary Needle Shoring.

STAP proceeded to design the Scaffolding and the Back propping to Floor Slabs during Demolition. This included Steel designs (Beam, Column & Connection).

STAP has continuously acted as Temporary Works checker for other sub-contractors designs on behalf of Soho House throughout the duration of this project.

STAP Structural Engineering Ltd - Expert Structural Engineers in London, Kent, and Surrounding Regions for Commercial and Residential Projects